The challenges of staging have been the primary objection from AAPS and their partners when it comes to considering other plans for constructing new Thurston. The district's current plan already calls for King to be staged to avoid construction, and in total encompasses 4 changes in schooling location. If we were to move forward with staging Thurston kids at new Logan, the logistical challenges add only 1 more change in location and would be minor and temporary.
Do you have concerns about our Thurston students trying to learn and teachers trying to teach less than 40 feet from a construction site for 4 years?
Sign up here for updates on this critical issue with the AAPS District's plan and how we can fix it!
No one is forced to learn or teach next to a loud, distracting construction site for 4 years - the majority of the time a new student would spend at Thurston!
The Thurston community will move into a new building in the same 2 school years as the District's current plan, and won't have to deal with construction during that time.
New Thurston, New Logan, and New King would be built on a schedule that will allow all students to be in new buildings by Bond Plan Phase 3.
The expansive green space that Thurston kids enjoy today would be preserved, including some of the biggest playgrounds and soccer fields in the district.
Much of the outdoor space that surrounds Thurston, including soccer fields, would likely still be available during construction.
Thurston Nature Center remains intact, including habitats that would be destroyed by the current AAPS plan.
Thurston students are not exposed to years of hazardous construction dust, or the constant noise of construction activity, which is not conducive to learning.
Logan has more time to plan for the safety of walking families who will need to cross Nixon to get to school when Logan moves to the East side of Nixon.
Logan & King students are delayed by 2 school years in their moves.
Thurston kids will need to be staged at a different school, which can create (minor and temporary) logistical challenges.
For a project of this size and scope, many eventualities need to be planned and budgeted for. The magnitude of changes caused by staging Thurston on the plan as a whole are minor - just the black boxes and arrows to the right. Logic and experience suggests that these would have a minimal impact on the overall project cost and time because:
The combination of the sinking fund and the bond allows for a lot more flexibility in the budget than just the bond alone, which is one of the reasons they were combined in 2019 when the bond was voted on. Even then, the combined expected revenue from these sources was roughly $200M short of the needed funds estimated for addressing the aging buildings. To address this, AAPS' plan stated that a future sinking fund should be passed to help cover the rest. Staying strictly under this arbitrary $1B cap was never the plan.
If it really is preferential to manage more new construction earlier in the schedule, then construction on a different school could be pulled up in order to minimize overall impacts. Hypothetically, Carpenter Elementary (red box) could be shifted earlier by 2-3 years, vacating the period that King is moved into while addressing the building that is listed as #1 in the district's facilities condition assessment priority list more promptly. Alternatively, Wines and the 4 other schools that rely on staging at old Wines could hypothetically be moved forward a year (purple boxes), shortening the total duration of the entire project through phase 3.
Here are the facts:
New Logan and new Thurston schools are both being built with the same student nominal capacity of 552 kids and maximum capacity of 624 kids. However, the current Thurston community currently uses 26 classes total - 2 pre-K / Young-5 rooms, 3 self-contained (ASD) rooms, and 21 K-5th grade classes, which won't fit into the 24 K-5th + 1 pre-K room that new Logan is being constructed with. Fortunately, the current Thurston population isn't who needs to fit, the 2027-2029 population is!
The combined 10 classrooms of the current 3rd, 4th, and 5th grade classes will have graduated to Clague by the time Thurston would need to stage at new Logan. During that same period, school-of-choice and in-district transfer enrollment could be managed for Thurston to keep the number of incoming classes to 3 rooms each. This does not affect the self-contained classes at all, assuming that as students graduate from these rooms this capacity is maintained for incoming kids. With this simple change, the current Thurston community remains wholly intact but can now fit into the new Logan building.
New Logan has one fewer pre-K room than Thurston would at this time, but considering that all the classrooms in the new buildings have attached bathrooms, adding the additional sink or accommodations to one room cannot be difficult or costly, and may benefit the Logan community as it is expected to grow tremendously over the next decade.
But it's also unfair to only subject Thurston to a learning environment right next to the distraction of construction for 3-4 years. Which of the options is worse when considering the outcomes for the three schools together?
With staging, the footprint of the new and current buildings could overlap substantially, even after adding in all the site improvements such as a separate bus loop, more drive-line distance, more parking, and the fire access lane around the building.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.